6.23 Commissioning report

B Confirm commissioning as complete; sign and date the
report.
Commissioning tasks
1.
Fill the heating system and check for leaks
2.
Have the details regarding water quality in the log been
observed?
- Concentration of additives
3.
Check the operating pressure
4.
Record gas parameters: Wobbe index
5.
Check the appliance equipment level
6.
Check the gas pipe for tightness
7.
Convert to a different gas type, if required
8.
Purge the gas line
9.
Check the ventilation and extract air apertures and the flue
connection
10.
Check the ventilation air diaphragm
11.
Switch on the heating system
12.
Record actual values:
- Draught
- Gross flue gas temperature t
- Air temperature t
L
- Net flue gas temperature t
- Carbon dioxide content (CO
Flue gas losses q
A
CO value, free of air
13.
Testing the gas supply pressure
14.
Function tests
– Check ionisation current
15.
Check for leaks during operation
16.
Fit sections of the casing
17.
Informing the user; handing over technical documentation
18.
Correct commissioning by the installing contractor
19.
User signature
Tab. 18 Commissioning report
Logano plus GB312 - Subject to technical modifications.
Calorific value
A
- t
A
L
) or oxygen content (O
2
Page
Actual values
24
Additives:
_________
28
29
_________ kW/m³
_________ kW/m³
29
30
30 ff.
32
32
33
33
37
Full load
_______Pa
______ °C
______ °C
______ °C
)
______ %
2
______ %
_____ ppm
39
____________ mbar
38
____________ μA
40
40
40
Signature:______________________
Signature:______________________
Commissioning
Comments
Yes:
Concentration:
_______%
Partial load
_______Pa
______ °C
______ °C
______ °C
______ %
______ %
_____ ppm
6
41