Commissioning report

▶ Check off preventive maintenance performed.
▶ Record measured values.
Commissioning steps
1.
Type of gas
2.
Check combustion air supply, air inlet and ventilation openings and flue gas
connection
3.
Check main gas orifice identification ( Tab. 13). Convert to a different gas type, if
necessary.
4.
Fill boiler with water and bleed complete heating system
5.
Measure the gas supply pressure [inches W.C.] or [mbar]
6.
Measure the orifice pressure and adjust if necessary [inches W.C.] or [mbar]
7.
Leak test during operation
Check ignition flame
Check main burner flame
Check that flue gas system is functioning properly
8.
Check maximum AquaSmart
9.
Install front wall of boiler
10.
Inform operator, hand over technical documentation
11.
Installer:
12.
Owners/operator:
Table 12 Commissioning report
Boiler size
38
45
55
64
Table 13 Main gas orifice identification
1) Factory setting
2) Convert from natural gas to propane gas only as described in Section 5.4.2, page 13.
Logano G234X – 6 720 811 233 (2014/05)
TM
setting
Main gas orifice identification (0...8500 ft /0...2591m)
1)
Natural gas
3.70
3.70
3.50
3.80
Placing the heating system in operation
Page
Comments or measured value
Natural Gas
Page 14
Page 23
Page 13
Page 20
Meas. value: _____________________________
Unit: _____________________________________
Page 20
Meas. value: _____________________________
Unit: _____________________________________
Page 18
Page 20
Page 20
Page 16
Page 22
Page 14
Page 22
Signature: _______________________________
Signature: _______________________________
LP (propane gas)
2.20
2.40
2.30
2.45
6
Propane Gas
2)
23