Manual commissioning

This screen shows the Site ID, the router's IP address (Terminal IP Address), and the
router's subnet mask (Terminal Subnet Mask).
2. If a printer is available, click
3. Give the printout to the customer.
The customer will need this information if they ever need to contact their service
provider for assistance. If no printer is available, advise the customer to record
this information and make sure they know where it is recorded. Make sure the
customer knows where this information is recorded.
Continue
4. Click
to download configuration parameters to the router.
A second Registration in Progress screen appears briefly (not shown here) while
the configuration parameters are downloaded. Then the Registration Complete
screen appears.
Restart
5. Click
on the Registration Complete screen.
This restarts the satellite router.
Figure 43: Registration complete – restarting the router
The Terminal Reset screen appears. (It is not shown here.)
Close
6. Click
on the Terminal Reset screen.
The router is now commissioned.
If satellite-based commissioning is not available, you must commission the router
manually. However, do not use the manual commissioning method unless you are
instructed to do so by the service provider.
Manual commissioning requires coordination between you and the Network
Operations Center (NOC). A technician enters parameters at the NOC, and you enter
the same parameters at the installation site. The NOC also downloads encryption
Print this Page
to print the Registration screen.