Chapter 3: Installing and Configuring the ITS

Step 1. Complete the ITS Installation Worksheets.

Photocopy and complete the following ITS installation worksheets provided in
Chapter 2 prior to installing any components:
• "ITS Infrastructure Equipment Summary Table" on page 2-26
• "ITS Access Point Equipment Summary Table" on page 2-26
• "APC Configuration Worksheet" on page 2-29
• "1.4 GHz Default AP Configuration Worksheet" on page 2-32
• "2.4 GHz Default AP Configuration Worksheet" on page 2-33
• "AP Group Configuration Worksheet" on page 2-35

Step 2. Install the ITS Infrastructure Components.

Figure 3-1 shows the suggested order when rack-mounting ITS infrastructure
components.
Note It is extremely important that you power and interconnect the ITS components only
in the prescribed order. Do not power up an ITS component or connect it to the
network until instructed to do so.
To install, power, and verify operation of the 1.4/2.4 GHz IntelliVue Telemetry
System Infrastructure components:
1. Referring to Figure 3-1, mount the ITS infrastructure components in a standard
19-inch equipment rack:
• Mount the ITS Access Point Controller above the ICN Network Switch.
• Mount the ITS Power over Ethernet unit beneath the ICN Network Switch.
• Mount the ITS Synchronization Unit beneath the ITS Power over Ethernet
3-4
Figure 3-1: Rack-mounting the ITS Infrastructure Components
Unit and above the UPS.
ITS Access Point Controller
ICN Network Switch
ITS Power over Ethernet Unit
ITS Synchronization Unit
Uninterruptible Power Supply

Hide quick links: