3 Tests and Diagnostics
3.3

Setting of the hardware configuration

To execute this program, select 2-Repair initial config test from the startup menu, press Enter
and follow the directions on the screen. The H/W initial information setting tool consists of three
subtests. Move the highlight bar to the subtest you want to execute and press Enter.
Subtest 01
Initial configuration
This subtest executes the following items and shows their contents in the display.
When an item ends normally, the program proceeds automatically to the next item.
When an error is found, the program stops and waits for key input. (After solving
the problem, it starts executing the item again.)
However, input the information when the DMI information appears. For details of
inputting DMI information, refer to "Subtest 08, DMI write" in the System test.
q Setting of the CPU set table
q Setting of the micro code
q Inputting or writing of DMI information (RAM, text)
q Setting of the HWSC
q Setting of the UUID
q Display of the DMI information (including UUID)
After completion of the above settings, the DMI information and the H/W
configuration & DMI information are appear in order. Check the contents and press
Enter.
Subtest 05
Digitizer FM write
This subtest rewrites the digitizer's firmware. When the version of the firmware is
under 45, this subtest rewrites the firmware. If the firmware's version is 45 or more,
no rewrite is executed in this subtest.
When the test ends, the display returns to the H/W initial information setting tool
menu automatically.
Subtest 08
System configuration display
This subtest displays the information of the system configuration.
When the following message appears, press Enter.
Press [Enter] key
3-8
3.3 Setting of the hardware configuration