Figure 2.1 Power Cable Socket Locations (Primequest2000 Series) - Fujitsu PRIMEQUEST 2000 Series Installation Manual

Primequest 2000 series
Hide thumbs Also See for PRIMEQUEST 2000 Series:
Table of Contents

Advertisement

CHAPTER 2 Preparing for Main Unit Installation
2.9 Connecting the Power Cables
- The cable is passed through the circle of release Thailand.
- Release tie is tightened and the power cable is fixed. The insulation connector is mistaken from the server and
does not come off.
Remark
Release tie can be detached by bending it with the choke end of the zip tie.
3.
Group all the cables that run outside the main unit and PCI_Box into power cables and signal cables, and secure
them firmly to the cable holders of the 19-inch rack with cable ties.
4.
Confirm that the AC power breaker is off. Then, connect the power cables to AC power. For details on the power
cable connections, see

FIGURE 2.1 Power cable socket locations (PRIMEQUEST2000 Series)

"2.4.2Facility power requirements and
characteristics".
7
CA92344-0536-01