Grid Director 4036/2036 Installation Manual
8

Operation

This chapter describes how to operate the 4036/2036 switch, once the installation is complete.
The 4036/2036 switch operation consists of making sure that it starts up properly and that any
initialization problems are resolved.
8.1

Powering on the 4036/2036 Switch

To start up the 4036/2036 unit:
The 4036/2036 chassis should be secured within the rack.
The InfiniBand cables should be plugged into the rear panel ports.
AC electrical circuit(s) should be available in preparation for connecting the 4036/2036 AC
cable(s).
Once the 4036/2036 chassis is secure within the rack, electrical cables from the power
distribution source can be fitted in preparation for connection.
Mellanox supplies two power cords, one per power supply unit.
To start up the 4036/2036 switch:
1. Ensure that all site power requirements have been met before connecting the chassis to a
power source.
2. Before turning on the power, verify that the power supplies and fan tray are properly
inserted.
3. At the rear of the 4036/2036 switch, plug the power cord into the power receptacle. Repeat
for the other power supply, if present.
4. Check that the power supply indicator light is green. Repeat for the other power supply, if
present.
5. Check for the following 4036/2036 switch status indicators:
PWR - Lights in green, indicating that the 4036/2036 switch is functional.
CAUTION: Ensure that all site power requirements have been met before connecting the
chassis to the power source.
IMPORTANT: Line cords should be connected to separate AC circuits for maximum
fault tolerance in the event of power problems.
NOTE: For more details regarding the unit's indicators, refer to
(on page 56).
4036/2036 Switch LED
55