5. Ensure that the clip nuts are already installed in the rack holes of the correct U level (on all
four vertical rack rails) as described in
(on page 33).
Note: Rack clip nuts are not provided by Mellanox.

Figure 17: Installing the clip nuts and placing the power cord

6. Place the power cords with the female connector facing the front of the rack (or the switch)
with approximately 10" hanging out of the front.
Route the other side (male connector) of the power cord to the rear of the rack. Do not
connect it to the PDU at this stage.
7. Lift and position the chassis, aligning the holes of all brackets with the rack holes of the
correct U level.
Gently push the switch inwards leaving it slightly protruded.

Figure 18: Inserting the switch into the rack

Measuring the Distance between Mounting Rails
37