Commissioning Checklist

Complete the installation and commissioning checklist below and make sure this manual is left
with the customer. Explain to the customer about the use and care of the unit and understands
the instructions and operation of the appliance.
Appliance positioned in a suitable location? (i.e. clearances, combustibles
etc.)
Was a Rinnai approved flue system installed and is the flue drawing
effectively?
Down rated (if applicable) according to data plate instructions?
Has specified gas pressures been checked and set?
Is the log set located correctly?
Has the appliance been tested for correct operation?
Is the customer fully aware of the operating procedure?