Agilent MOI for MHL Cables Compliance Tests
5.4. Measurement
5.4.1. Differential Intra-Pair Skew
1. Connect DUT (Figure 5-1).
Figure 5-1. Differential Intra-Pair Skew Test Setup
Note: Unused fixture pots should be terminated with 50 ohm terminators.
2. Select
Trace
3.
3. Press
Stop
Single.
4. Click
Auto Scale
transition point of x-axis (in sec).
5. Click the box below the right knob under Horizontal. Set the horizontal value to the
above transition point in a dialog box, so that the transition point can be centered.
6. Select
Trace 9
and repeat the same operations, step 4 to 5.
7. Select
Trace
3.
8. Click
Marker Search
Δ
9. Check the
Time.
10. Select
Target (Stop)
and select "X & Y" for auto scaling the x-axis and y-axis. Record the
Δ Time
and select
to Trace 9 (T42).
to show the dialog box.