Cause
The updater has detected more than the default maximum number of transactions
that need to be undone. This exceeds the number of transactions that can currently be loaded
into memory.
Effect
The updater abends, and the takeover operation aborts.
Recovery
If this happens during a takeover operation, reissue the TAKEOVER command.
When the updater restarts the table will automatically be resized to accommodate the required
number of transactions. If this happens in a stop-update-to-time operation, restart RDF and
issue a new STOP UPDATE, TIMESTAMP command at a time when there are fewer transactions
active.
900
Extractor has finished ZLT processing
Cause
The extractor has sent all remaining audit from the remote mirror(s) on the ZLT
standby system to the backup system.
Effect
The extractor shuts down.
Recovery
This is an informational message; no recovery is required.
901
Extractor is started for ZLT processing
Cause
The extractor is started on the ZLT standby system for ZLT processing.
Effect
The extractor reads and sends all remaining audit from the remote mirror(s) connected
to the ZLT standby system to the receiver on the backup system.
Recovery
This is an informational message; no recovery is required.
902
The remote mirror for volume is missing
volume
is a volume name.
Cause
The extractor has determined that the specified remote mirror is not connected to the
ZLT standby system or that an expected audit trail file is missing.
Effect
The extractor abends.
Recovery
Connect all required remote mirrors to the ZLT standby system and then re-issue
the RDF TAKEOVER command. If you have already connected all remote mirrors and you
get this event, then you already have all audit needed for the takeover operation. To allow the
takeover operation to complete, disable the REMOTE MIRROR attribute in your RDF
configuration with this RDFCOM command: ALTER RDF REMOTE MIRROR OFF. Then
re-issue the RDF TAKEOVER command.
903
Receiver has finished ZLT processing
Cause
All remaining audit from the ZLT standby system has been received and stored in
the image trails for this receiver.
Effect
If this message comes from the master receiver, then normal RDF TAKEOVER
processing is ready to proceed. If it comes from an auxiliary receiver, then normal RDF
TAKEOVER processing does not start until the master receiver has finished ZLT processing.
Recovery
This is an informational message; no recovery is required.
904
Auxiliary receiver is catching up
Cause
The master receiver has found a TMF shutdown record. The auxiliary receiver reporting
this event is working to catch up to the corresponding point.
RDF Messages
407

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nonstop rdf h-series rvusNonstop rdf

Table of Contents