SmartLane
MAINTENANCE C
Every three years or 3,000,000 cycles, whichever comes first.
Time required: 2 hours/unit
MAINTENANCE ACTIVITIES (REPLACE PARTS AS REQUIRED)
CHECK
All points included in MAINTENANCE A
REPLACE
The rubber release stop in case of power failure. ( Chap. 8.23, page 80)
Single balancing spring assembly (narrow unit)
The closing flap ( Chap. 8.12, page 66)
The guide strip of the closing flap
MAINTENANCE D
Every four years or 4,000,000 cycles, whichever comes first.
Time required: 1 hour ½ / unit.
MAINTENANCE ACTIVITIES (REPLACE PARTS AS REQUIRED)
CHECK
All points included in MAINTENANCE A
REPLACE
The rubber release stop in case of power failure. ( Chap. 8.23, page 80)
The double balancing spring assembly (large unit)
MAINTENANCE E
Every five years or 5,000,000 cycles, whichever comes first.
Time required: 1 hour/unit.
MAINTENANCE ACTIVITIES (REPLACE PARTS AS REQUIRED)
CHECK
All points included in MAINTENANCE A
REPLACE
The rubber release stop in case of power failure. ( Chap. 8.23, page 80)
Kinematic end stops.
89