5 Electrical Connection
Note the following items when laying out cables on site:
The axial tension on PV connectors must not exceed 80 N. Avoid axial cable
stress on the connector for a long time during field wiring.
Radial stress or torque must not be generated on PV connectors. It may cause
the connector waterproof failure and reduce connector reliability.
Leave at least 50 mm of slack to avoid the external force generated by the cable
bending affecting the waterproof performance.
Refer to the specifications provided by the cable manufacturer for the minimum
cable bending radius. If the required bending radius is less than 50 mm, reserve
a bending radius of 50 mm. If the required bending radius is greater than 50 mm,
reserve the required minimum bending radius during wiring.

5.7.1 PV Input Configuration

As shown in the figure below, the inverter is provided with multiple PV inputs, and each
PV input is designed with an MPP tracker.
Each PV input operates independently and has its own MPPT. In this way, string struc-
tures of each PV input may differ from each other, including PV module type, number of
PV modules in each string, angle of tilt, and installation orientation.
A maximum of two PV strings can be connected to an MPPT controller. For the best use
of PV power, the type, quantity, tilt, and orientation of PV modules connected to the same
MPPT shall be the same.
Prior to connecting the inverter to PV inputs, the specifications in the following table should
be met:
48
figure 5-4 PV Input Configuratinon