Check whether the optimizers have all been recognized successfully; if not, you may
add them manually. Tap
the blank area of the canvas, complete the required information, and tap Add.
5
Choose the module that has been added, and tap Assign to associate it with the
corresponding S/N.
Step 3 Add a Meter:
1
Tap
at the bottom of the screen.
2
Choose Meter, and tap the blank area of the canvas. Then, set the number, and tap Add.
3
Choose the meter that has been added, and tap Assign to associate it with the
corresponding S/N.