Electrical Connection Overview - Sungrow SG25CX-P2 User Manual

Pv grid-connected inverter
Hide thumbs Also See for SG25CX-P2:
Table of Contents

Advertisement

5 Electrical Connection
table 5-1 The label of COM2 terminal
DI
DI
DI
PGND
PGND
table 5-2 The label description of COM2 terminal
No.
Label
1
DI
2
DRM
3
DO
RS485 (A1, B1)
4
Meter (A2, B2)
5
(1) When the inverter is connected to a third-party monitoring device, please confirm which
communication interface is used, and whether it will cause loss of certain functions of the
inverter.
5.3

Electrical Connection Overview

Connecting the inverter to the PV system requires connecting the inverter to the protective
grounding point, to the grid, and to the PV strings.
(A)PV string
(D)Grid
36
DRM
C
D4/8
D2/6
R
D3/7
D1/5
Description
emergency stop dry contact
"AU"/"NZ": Demand response enabling device
(DRED)
"DE": Ripple Control Receiver (RCR)
fault output dry contact
Connect to the Logger, so as to implement data ex-
change with PC or other monitoring devices.
(1)
Enable the communication between inverters in
parallel.
(1)
Connect to the Smart Energy Meter.
(B)Optimizer(optional)
(E)Monitoring device
DO
RS485
COM
B1
B1
NO
A1
A1
(C)Inverter
(F)AC circuit breaker
User Manual
Meter
B2