Commissioning

13.2 Check before powering on for the first time

13.2
Check before powering on for the first time
Check before powering on for the first time
Before the first power-on, check that the SIMATIC Drive Controller and the SINAMICS
components are correctly installed and wired.
Installation and wiring
• Have the required minimum clearances for heat dissipation been provided?
• Are all front connectors wired according to the circuit diagram and inserted in the correct
connection?
Grounding and chassis concept
• Is the protective conductor terminal on the SIMATIC Drive Controller connected to the
protective conductor?
• Have all cable shields been applied?
• Are the required equipotential bonding cables connected with low impedance to the
affected plant units?
Further information
You can find information on assembly/installation and commissioning of SINAMICS S120
components in the SINAMICS S120 manuals and in the EMC Installation Guide.
(https://support.industry.siemens.com/cs/ww/en/view/60612658)
13.3

Commissioning procedure

13.3.1

Removing/plugging in a SIMATIC memory card

Requirements
The SIMATIC Drive Controller only supports pre-formatted SIMATIC memory cards. If
applicable, delete all previously stored data before using the SIMATIC memory card.
In order to work with the SIMATIC memory card, first ensure that the SIMATIC memory card is
not write-protected. For this purpose, slide the slider on the SIMATIC memory card out of the
lock position.