STANDARD SYSTEM INSTALLATION
Standalone UPS Initial Startup
88
Eaton BladeUPS (12 kVA) User's Guide
Figure 70. Connecting UPSs to the BladeUPS Bar (Bottom Entry Shown)
To start up a standalone UPS:
NOTE Verify that the total equipment ratings do not exceed the UPS capacity to prevent an overload alarm.
1.
Plug the equipment to be protected into the UPS, but do not turn on the
protected equipment (see Figure 58 on page 71).
2.
Make any necessary provisions for cord retention and strain relief.
3.
Verify that all UPS circuit breakers are in the OFF (O) position.
NOTE The load connector breaker controls the load connector only, not the output power cord.
4.
Verify that the UPS power cord is plugged in.
5.
Switch on utility power where the UPS is connected.
6.
Remove the breaker ties from the circuit breakers.
7.
Switch the UPS input circuit breaker to the ON (
S
164201649 Rev 6 www.eaton.com/powerqualtiy
Plug Retainer
1
2
3
| ) position.