Rack Setup For The Ebm - Eaton Powerware BladeUPS User Manual

12 kva
Hide thumbs Also See for Powerware BladeUPS:
Table of Contents

Advertisement

PREASSEMBLED SYSTEM INSTALLATION
34
Eaton BladeUPS (12 kVA) User's Guide

Rack Setup for the EBM

The EBM is heavy (see page 130). Removing the EBM from its carton requires a minimum of two people. Use
the corrugated lifting sling (packaged with the UPS) to move the UPS.
NOTE Mounting rails are required for each individual cabinet.
To install the EBM rail kit:
1.
Loosen the assembly wing nuts on both rail assemblies and adjust the rail size
for the depth of your rack (see Figure 19).
Front
Rail Assembly
2.
Select the proper holes in the rail for positioning the EBMs in the rack.
Place the first rail for the first EBM above the UPS, using positions 37 and 42 for
the front hex-head screws. If you are installing additional rails, place the next rail
4 holes above the last installed screw (see Figure 20).
NOTE Verify that the hole patterns on the rails and mounting brackets align with the hole pattern on the
rack.
S
164201649 Rev 6 www.eaton.com/powerqualtiy
C A U T I O N
Assembly Wing Nuts
Figure 19. Adjusting the Rail Depth
Rear

Advertisement

Table of Contents
loading

Table of Contents