OPERATION
!
WARNING
All information in this manual is for
reference and guidance purposes,
and does not substitute for required
professional training, conduct,
and strict adherence to applicable
jurisdictional/professional codes
and regulations.
Non-Fulton product information
is for reference purposes only. No
Fulton document should substitute
for full review of documentation
available from the component
manufacturer.
3-16

` SECONDARY PUMPS

This screen will only be accessible if Secondary Pumps is selected. See Auxiliary
Con guration.
Pumps may be con gured to maintain either system delta-P or delta-T. Rotation
is automatic.
ƒ Lead/Lag
Integrated multiple boiler sequencing "Lead/Lag" is con gured and monitored
through this category and Admin. Ensure the boilers are on a private Ethernet/IP
network shared with no other devices before continuing setup.
To function properly on the network, the Local Ethernet/IP Address of each
boiler must be speci cally set on the System Con guration screen in the Admin
category:
Boiler 1 – 192.168.1.100
Boiler 2 – 192.168.1.101
Boiler 3 – 192.168.1.102
Boiler 4 – 192.168.1.103
Boiler 5 – 192.168.1.104
Physical wiring of the local boiler network uses Ethernet Port 1. Wiring for the
Ethernet/IP network will change based on the number of boilers in the system.
For systems with two boilers, a single shielded Ethernet cable can be wired
directly between the boilers. For systems with more than two boilers, each boiler
will need to have a shielded Ethernet home run back to the Ethernet switch
(ships loose in trim kit when ordered).
To enable Lead/Lag functionality, use the Auxiliary Con guration screen under
the Admin category. Set the Number of Boilers eld to the number of boilers
to be controlled. These steps must be completed at each boiler. Ensure the
Universal Data, also under Admin, is properly con gured for data sources.

` LEAD/LAG CONFIGURATION

This screen is used to set sequencing preferences.
ƒ
Lead/Lag priority determines how the boilers are sequenced, either by
cycles only, hours only, or an optimized algorithm.
ƒ
Number of boilers displays how many boilers the Lead/Lag system expects
to have under control.
ƒ
Lead start is how far below setpoint before the lead boiler turns on.
ƒ
Lead stop is how far above setpoint before the lead boiler turns o .
ƒ
The aggressive-passive slider determines how quickly lag boilers are
enabled, , and how quickly the burner(s) ramp up to meet setpoint. A
passive setting will provide more damped setpoint response.
EDR-PURE-IOM-230608
Boiler 6 – 192.168.1.105
Boiler 7 – 192.168.1.106
Boiler 8 – 192.168.1.107
Boiler 9 – 192.168.1.108
Boiler 10 – 192.168.1.109