2.6.1.5 SN2100 Splitting Options
All QSFP28 ports are splittable. Each port can be split to 4xSFP28 (10/25G) or 2xQSFP28
(50G) ports. There are no blocking requirements.
2.6.1.6 SN2010 Splitting Options
All QSFP28 ports are splittable. Each port can be split to 4xSFP28 (10/25G) or 2xQS-
FP28(50G) ports each. There are no blocking requirements.
2.7

Initial Power On

Each system's input voltage is specified in the
be standard 3-wire AC power cords including a safety ground and rated for 15A or higher.
Plug in the first power cable.
Step 1.
Plug in the second power cable.
Step 2.
Wait for the System Status LED to turn green.
Step 3.
Rev 2.2

Figure 51: SN2100 Splitting Options

The system platform will automatically power on when AC power is applied. There is
no power system. Check all boards, power supplies, and fan tray modules for proper
insertion before plugging in a power cable.