1.15
Provision IP Network Settings on the SCU
If the Total Access 3000/3010 shelf has a SCU and is to be connected to an IP network
for TELNET, TFTP, or SNMP management, there are several IP parameters that need
to be set for the shelf to communicate with the network.
1.16
Route Fiber Through the Total Access 3000/3010 Heat
Baffle
Total Access 3000/3010 can serve the local loop with an optical DS2 transport to
deliver up to four T1s out to the customer premises. (See APP 333, Fiber-Optic Loop
Applications, of this system manual.) In this application, the transport is fiber optics
out to the customer via a pair of single-mode fiber optic cable from the front of the
QFO-C access module, across to the left side of the shelf (viewed from the front), and
to the CO overhead fiber routing system.
1.17
Follow-up Procedures
Once this procedure is complete, the Total Access 3000/3010 shelves should be ready
for acceptance testing. Please locate the tab labeled "Acceptance Test Procedures" and
proceed with ATP-601, Acceptance Test Procedure for Total Access 3000/3010 Shelf,
CO Installation.
© 2002, ADTRAN, Inc.
For details, go to: DLP-718.
For details, go to: DLP-719.
Total Access
®
3000/3010 System Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Total access 3010

Table of Contents