Huawei FusionCol8000-E260 Quick Manual page 49

Modular indirect evaporative cooling system
Hide thumbs Also See for FusionCol8000-E260:
Table of Contents

Advertisement

FusionCol8000-E260 Modular Indirect Evaporative
Cooling System
Quick Guide (FDC Scenario)
Procedure
Step 1 Refer to
Figure 9-2 Installing air ducts
----End
Issue 01 (2022-06-30)
For connections between the air ducts, flexible connections, air dampers,
unit, and building, the bolt spacing should not exceed 150 mm and all
connection seams should be sealed with sealant.
The external surfaces of air ducts, flexible connections, and air dampers
should be mounted with a thermal insulation foam of at least 30 mm
thick and a protective layer of at least 0.5 mm thick for long-term
outdoor application.
After the air ducts are installed, perform light leakage testing.
A Physical Ports
NO TE
● The air duct must be wrapped with thermal insulation foam, and the thickness of the
thermal insulation foam must be greater than or equal to 3 cm.
● The joint between the air ducts and the unit should be sealed to prevent air leakage and
water leakage.
Copyright © Huawei Digital Power Technologies Co., Ltd.
and secure the air ducts to the unit using screws.