FusionCol8000-E260 Modular Indirect Evaporative
Cooling System
Quick Guide (FDC Scenario)
Procedure
Step 1 Refer to
Figure 9-2 Installing air ducts
----End
Issue 01 (2022-06-30)
–
For connections between the air ducts, flexible connections, air dampers,
unit, and building, the bolt spacing should not exceed 150 mm and all
connection seams should be sealed with sealant.
–
The external surfaces of air ducts, flexible connections, and air dampers
should be mounted with a thermal insulation foam of at least 30 mm
thick and a protective layer of at least 0.5 mm thick for long-term
outdoor application.
–
After the air ducts are installed, perform light leakage testing.
A Physical Ports
NO TE
● The air duct must be wrapped with thermal insulation foam, and the thickness of the
thermal insulation foam must be greater than or equal to 3 cm.
● The joint between the air ducts and the unit should be sealed to prevent air leakage and
water leakage.
Copyright © Huawei Digital Power Technologies Co., Ltd.
and secure the air ducts to the unit using screws.
9 Installing Air Ducts
43