Position of the switch-disconnector (1) for the battery power
supply with pos. 2: Outlet distributors (Batt). Observe the
warning notices!
Connect the lines for the battery power supply of a substa-
tion:
Make sure that the system and the supply lines are discon-
nected and secured!
Lay the supply lines to/from the 40071361670 switch cabi-
net and in its cable ducts and to/from the substation switch
cabinet.
Connect the positive conductor to the positive terminal of
the outgoing distributor.
Connect the negative conductor to the negative terminal of
the output distributor.
When retrofitting fuse elements, the enclosed sticker must
be applied with the correct polarity to identify the connections
as shown in the illustration.
Mounting- and Operating Instruction Eaton LoadStar-S JSB 40071860396 March 2021 www.ceag.de
Connection of a temperature sensor
A temperature sensor (for temperature monitoring of the
battery bank) of the 40071361670 central battery system is
2
1
mandatory for emergency lighting systems with a central
battery. Connection to the charging unit is made in the control
cabinet via terminals (1) F+ and F- on the 3-level installation
terminals with spring-cage connection.
Lay the temperature monitoring cable between the battery
bank and the 40071361670 switch cabinet and connect it to
the switch cabinet via its 3-storey installation terminals with
tension clamp connection.
Position of the terminal block for connecting a temperature
sensor
A shielded 2-wire cable must be used as the connecting
cable for the temperature sensor. In the system, the shield
must be connected to the protective conductor terminal on
one side via a shield quick connector.
6 Assembly and installation of the LoadStar-S
1
ATTENTION!
17

Advertisement

Table of Contents
loading

Table of Contents