4.14 SHUT DOWN AND PARK

To shut down and park the machine, the procedures are as fol-
lows:
1.
Drive machine to a reasonably well protected area.
2.
Ensure boom is fully retracted and lowered over rear axle.
3.
Shut down Emergency Stop at Platform Controls.
4.
Shut down Emergency Stop at Ground Controls. Position
Platform/Ground Select switch to center Off.
5.
If necessary, cover Platform Controls to protect instruction
placards, warning decals, and operating controls from hos-
tile environment.
IF PARKING A MEWP WITH THE BOOM ELEVATED IN AN EFFORT TO CONSERVE SPACE,
BOOMS MAY BE ELEVATED, BUT SHALL NOT BE EXTENDED. IT IS THE OPERATOR'S
RESPONSIBILITY TO ENSURE ALL SAFETY PRECAUTIONS IN SECTION 1 OF THIS MAN-
UAL ARE FOLLOWED FOR EACH UNIQUE SITUATION.
31215054
SECTION 4 - MACHINE OPERATION

4.15 LIFTING AND TIE DOWN

See Figure 4-7.

Lifting

1.
Refer to the Serial Number Plate, refer to the Specifications
section of this manual, or weigh the individual unit to find
the Gross Vehicle Weight.
2.
Place the boom in the stowed position with the turntable
locked.
3.
Remove all loose items from the machine.
4.
Properly adjust the rigging to prevent damage to the
machine and so the machine remains level.

Tie Down

WHEN TRANSPORTING THE MACHINE, THE BOOM MUST BE FULLY LOWERED INTO
THE BOOM REST.
NOTE:
Prior to loading the machine onto a trailer, it will be necessary to
rotate the turntable 180 degrees to provide better weight distri-
bution.