4.22 SHUT DOWN AND PARK

The preferred procedures to shut down and park the machine are as follows:
1. Drive machine to a reasonably well protected area.
2. Ensure boom is fully retracted and lowered over rear axle.
3. Shut down Emergency Stop at Platform Controls.
4. Shut down Emergency Stop at Ground Controls. Position Platform/Ground Select
switch to center OFF (center position).
5. If necessary, cover Platform Controls to protect instruction placards, warning
decals, and operating controls from hostile environment.
If parking a MEWP with the boom elevated in an effort to conserve space, booms
may be elevated, but shall not be extended. It is the operator's responsibility to
ensure all safety precautions in Section 1 of this manual are followed for each
unique situation.

4.23 LIFTING AND TIE DOWN

4.23.1
Lifting
1. Refer to the Machine Serial Number Plate, call JLG Industries, or weigh the
individual unit to find out the Gross Vehicle Weight.
2. Place the boom in the stowed position.
3. Remove all loose items from the machine.
4. Properly adjust the rigging to prevent damage to the machine and so the
machine remains level.
4.23.2
Tie Down
When transporting the machine, the boom must be fully lowered into the boom
rest.
1. Place the boom in the stowed position.
2. Remove all loose items from the machine.
3. Secure the chassis using straps or chains of adequate strength.