1MRK 505 287-UUS B
3 = Faulty
4 = Not in use
5 = All
PSTO = All, then it is no priority between operator places. All operator places are allowed to
operate at the same time.
According to IEC61850 standard the
Table 16:
Value
0
1
2
3
4
5
6
7
8
Switch controller (SCSWI)
The Switch controller (SCSWI) initializes and supervises all functions to properly select and
operate switching primary apparatuses. The Switch controller may handle and operate on one
three-phase device.
After the selection of an apparatus and before the execution, the switch controller performs the
following checks and actions:
A request initiates to reserve other bays to prevent simultaneous operation.
Actual position inputs for interlocking information are read and evaluated if the operation is
permitted.
The synchronism check/synchronizing conditions are read and checked, and performs
operation upon positive response.
The blocking conditions are evaluated
The position indications are evaluated according to given command and its requested
direction (open or closed).
The command sequence is supervised regarding the time between:
Select and execute.
Select and until the reservation is granted.
Execute and the final end position of the apparatus.
Execute and valid close conditions from the synchronism check.
At error the command sequence is cancelled.
Busbar protection REB650
Application manual
orCat attribute according to IEC61850
Description
not-supported
bay-control
station-control
remote-control
automatic-bay
automatic-station
automatic-remote
maintenance
process
© Copyright 2013 ABB. All rights reserved
4,5,6
1,2,3,4,5,6
orCat attribute in originator category are defined in
Section 10
Control
Table 16
M16596-3 v4