PARTS REQUIRED:
x13
1-1/2" (3,8 cm)
BEGIN
Place 2nd 12' eave wall centered on floor
1
1-1/2" (3,8 cm) overlap is to the top.
ENSURE PANEL CORNERS ARE FLUSH.
2
Secure wall with (1) 2" screw through
eave wall panel into 12' gable wall
bottom and top plates (Fig. B, Fig. A).
Secure wall to bottom plate first.
3
Nail lower edge of wall panels
to floor frame with 2" nails
spaced 6" apart.
Angle nails into floor frame
(Fig. C).
Secure wall bottom plates to floor
with 3" nails (Fig. C).
4
Nail 12' eave wall panel to 12' gable wall
stud with 1-1/2" nails spaced 6" apart.
5
Secure wall top plate with (1) 3" screw at the
corner at an angle as shown (Fig. D).
FINISH
Your 2nd 12' eave wall is now installed.
2nd 12' EAVE WALL INSTALLATION
x2
2" (5,1 cm)
x27
2" (5,1 cm)
6"
(15,2 cm)
2" (5,1 cm)
Nails
x12
x1
1-1/2"
(3,8 cm)
3" (7,6 cm)
Nails
Nail 2" nails first.
3" (7,6 cm)
Nails
Fig. C
2" (5,1 cm)
Screw
30
3" (7,6 cm)
3" (7,6 cm)
Fig. B
2" (5,1 cm)
Screw
Fig. A
3" (7,6 cm)
Screw
Fig. D
6" (15,2 cm)
1-1/2" (3,8 cm)
Nails
Flush

Advertisement