Procedure C - YASKAWA PROFINET JOHB-SMP3 Technical Manual

Hide thumbs Also See for PROFINET JOHB-SMP3:
Table of Contents

Advertisement

8.
Set drive parameters in

Procedure C

This section shows the procedure to install and wire the option on a GA700, GA800 or CR700 drive.
Prepare the Drive for the Option
Correctly wire the drive as specified by the manual packaged with the drive. Make sure that the drive functions
correctly. Refer to the drive manuals for more information.
A - Insertion point for CN5 connector
B - Option
C - Included screws
D - Drive front cover
E - Keypad connector
F - Keypad connector tab
G - Holder
H - LED label
Install the Option
DANGER
Electrical Shock Hazard. Do not examine, connect, or disconnect wiring on an energized drive. Before
servicing, disconnect all power to the equipment and wait for the time specified on the warning label at a minimum. The internal
capacitor stays charged after the drive is de-energized. The charge indicator LED extinguishes when the DC bus voltage
decreases below 50 Vdc. When all indicators are OFF, measure for dangerous voltages to make sure that the drive is safe. If
you do work on the drive when it is energized, it will cause serious injury or death from electrical shock.
NOTICE
Damage to Equipment. When you touch the option, make sure that you observe correct electrostatic
discharge (ESD) procedures. If you do not follow procedures, it can cause ESD damage to the drive circuitry.
Note:
You can only install this option into the CN5-A connector on the drive control board.
1.
Put the LED label (H) in the correct position on the drive front cover (D).
2.
Shut off power to the drive and wait for the time specified on the drive warning label at a minimum.
Make sure that the charge indicator LED is unlit, then remove the keypad and front cover. Refer to the
drive manuals for more information.
YASKAWA SIEP C730600 0KA PROFINET Technical Manual
Related Drive Parameters on page 22
Figure 5.6 Drive Components with Option
for correct option performance.
I - Keypad
J - LED Status Ring board temporary placement
holes
K - Option modular connector CN1B (Port 2) (RJ45)
L - Option modular connector CN1A (Port 1) (RJ45)
M - LED Status Ring board
N - Connector CN5-A
O - Connector CN5-B (Not available for
communication option installation.)
P - Connector CN5-C (Not available for
communication option installation.)
5 Installation Procedure
17

Advertisement

Table of Contents
loading

Table of Contents