PARTS REQUIRED
x23
2" (5,1 cm)
x13
1-1/2" (3,8 cm)
BEGIN
1
Place 10' eave wall centered on floor.
1-1/2" (3,8 cm) overlap is to the top.
Secure wall with (1) 2" screw into 10' wall
bottom plate (Fig. A) and top plate (Fig. B).
Secure wall to bottom plate first.
ENSURE PANEL CORNERS ARE FLUSH.
Nail lower edge of panels to floor with 2" nails
2
spaced 6" apart.
Angle nails into floor frame (Fig. C).
Nail panel to 10' wall stud with 1-1/2" nails
spaced 6" apart.
Secure wall top plate with (1) 3" screw
3
angled at the corner at an angle as shown
(Fig. D).
FINISH
Your 1st 10' eave wall is now installed.
1st 10' EAVE WALL INSTALLATION
x1
3" (7,6 cm)
x10
1-1/2" (3,8 cm)
3" (7,6 cm)
Nails
Nail 2" nails first.
2" (5,1 cm)
Nails
Fig. C
3" (7,6 cm)
Flush
2" (5,1 cm)
Screw
Fig. A
6" (15,2 cm)
Nails
6"
(15,2 cm)
28
x2
2" (5,1 cm)
Fig. B
3" (7,6 cm)
Screw
Fig. D
3" (7,6 cm)
Nails
2" (5,1 cm)
Nails
2" (5,1 cm)
Screw