Example: Assembling
top units for
busbar voltage
transformer 4MU4
861-9601.9 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DA10 • Revision 11
Fig. 55:
Inserting the busbar
Busbar in the fixed-mounted panel
Upper connecting bar
Upper disconnector contact
Cup head bolt with hexagon nut and conical spring washer (5x)
Busbar in the panel to be lined up
Lower disconnector contact
Lower connecting bar
➭ Prepare the flanges of the busbar housing, and bolt them together.
➭ Align the busbar and the connecting bars so that the busbar section is in line and the bolts
fit through the hole.
Fig. 56:
Bolting the busbar and the connecting bars
together
➭ Tighten the bolts in this busbar section (tightening torque: 40 Nm).
Installation
Upper connecting bar
Cup head bolt with hexagon nut
and conical spring washer
M10x85 (1x)
Cup head bolt with hexagon nut
and conical spring washer
M10x65 (4x)
Busbar in the panel to be lined
up
Lower connecting bar
Busbar in the fixed-mounted
panel