Lifting unpacked
transport unit with
transport pallet
Removing the transport
unit from the transport
pallet
Lifting unpacked
transport unit with
transport pallet
54/214
➭ Knock the boards marked at the front out of the transport pallet by means of the fork-lift
truck.
Fig. 31:
Example for lifting the transport unit with the fork-lift truck on an individual
panel
Boards marked at the front
➭ Lift the transport unit with a crane, hydraulic jacks or a fork-lift truck.
Remove the transport unit from the transport pallet only if
• there are only short transportation ways left, or
• the transport unit can be directly set down at the place of use.
The transport unit is screwed onto the transport pallet. The fixing points for transport are
located behind the front metal cover in the frame, at the rear cross member and at the lateral
parts of the frame.
➭ Remove front cover sheets from the subframe of the panel.
➭ Remove all fixing bolts that connect the transport unit with the transport pallet.
To lift the switchgear, use two lifting rods with a diameter of 30 mm.
Minimum length of the lifting rods: Width of transport unit plus 400 mm.
Certified lifting rods for different panel widths are available at the regional Siemens
representative.
Fig. 32:
Certified lifting rod for panels of 8DA10
Lifting rod with termination plate
Lock washer
Retaining element