861-9601.9 • INSTALLATION AND OPERATING INSTRUCTIONS • 8DA10 • Revision 11
De-earthing the feeder
1
Initial situation
3
Push the interrogation lever downwards.
5
Switch the three-position disconnector from
READY-TO-EARTH to OPEN position (insert the
operating lever for the READY-TO-EARTH function
and turn 180° counter-clockwise).
2
Remove the padlock at the "feeder earthed"
locking device.
Open the circuit-breaker to de-earth the feeder.
4
Push the control gate to the right.
6
Remove the operating lever for
the READY-TO-EARTH function.
The interrogation lever and the control gate return to
their initial position.