5. When the USB interface is appropriately set, then the "Accessible nodes" screen form shows
the converters that can be accessed.
If you have not correctly set the USB interface, then the following "No additional nodes
found" message is displayed. In this case, follow the description below.
6. Transfer the converter into the project using the menu: "Online - Upload device as new
station (hardware and software)".
You have transferred a converter accessible via the USB interface into your project.
Procedure
1. Select your project and go online:
2. In the following screen form, select the converter with which you wish to go online.
3. Once you are online, select "Commissioning" → "Commissioning Wizard":
You have started the commissioning Wizard of the converter.
5.5.3

Carrying out quick commissioning

Procedure
Select whether the converter is connected to a higher-level control via the fieldbus.
Select whether the ramp-function generator for the speed setpoint is implemented in the higher-
level control or in the converter.
Select the control mode.
Converter with the control units CU240D-2
Operating Instructions, 10/2020, FW V4.7 SP13, A5E34262100B AH
Commissioning
5.5 Quick commissioning with a PC.