System Operation; Switch On; Switch Off - Alpha ESS Storion-SMILE-T10 Installation Manual

Energy storage system
Hide thumbs Also See for Storion-SMILE-T10:
Table of Contents

Advertisement

Step 5:
Set the communication address and communication baud rate in the
communication setting interface. When the meter is used as the Grid meter (DC,
AC/Hybrid system), the address is set to "005". When it is used as the PV meter
(AC/Hybrid system), the address is set to "006". The baud rate is set to 9600;

System Operation

3.1 Switch on

System shall be turned on in the correct sequence to avoid any damage.
Step 1:
Step 2:
Step 3:
Turn on the PV switch (DE: PV switch on inverter; AU: external PV switch)
Step 4:
If backup load is applied, turn on the external Backup AC breaker

3.2 Switch off

System shall be turned off in the correct sequence to avoid any damage.
Step 1:
Step 2:
Step 3:
Step 4:
switch)
Step 5:
Turn on the MCCB and the AC switch of HV50056 shows.
Turn on the external On-grid AC breaker
Remove the front panel of the inverter and HV50056
If backup load is applied, turn off the Backup AC breaker.
Turn off the MCCB of HV50056 and the ac switch on HV50056
Turn off the PV switch (DE: PV switch on inverter; AU: external PV
Turn off the On-grid AC breaker.
42 / 55