Terminal block requirements

Installing the cross-connect terminal

553-3121-210
Standard 3.0
Chapter 14 – Installing and connecting the cross-connect terminal
The cross-connect terminal requires sufficient connecting blocks to terminate
the following wires:
up to six 25-pair cables from each NTMW08 cabinet and up to ten
25-pair cables from each NTMW35 cabinet.
— Each trunk or line circuit card requires a cable. Allow for additional
cables at the cross-connect terminal if any of the PE slots are initially
left vacant.
wiring from telephones and trunks
Always use caution when installing or modifying telephone lines.
Avoid installing telephone wiring during a lightning storm. Never
touch uninsulated telephone wiring unless the line has been
disconnected at the network interface.
Procedure 12 describes how to install the cross-connect terminal.
Procedure 12
Installing the cross-connect terminal
1
Consult the equipment layout plan to determine where the
cross-connect terminal should be located
2
Install the terminal blocks in a layout similar to that shown in the
Figure
30.
If installing the BIX system, refer to BIX Installation and Servicing
(NTP 631-4511-200).