31. Use RT schematic drawing SD-7C118-01 to check wiring. Check for tip and
ring reversal between RT and cross-connect terminal. Correct wiring problem
and repeat Step 25 until tests pass and continue with Step 32.
32. Is this the last designated channel to be tested with TBCU?
If YES, then continue with Step 33.
If NO, then proceed to Step 25.
33. At RT, remove test telephone and reinstall the protector unit for the customer
drop.
STOP. YOU HAVE COMPLETED THIS PROCEDURE.