Lucent Technologies SLC 5 Series Manual page 189

Carrier system
Table of Contents

Advertisement

Power Up: DLP-524
Page 8 of 8
OPEN BAT
TEST
BATC
BAT1
BAT2
BAT3
BAT4
OPEN BATTERY TEST
TO MEASURE * USE TEST POINTS
BATTERY CURRENT:
Battery 1 * bat1 - batc
battery 2 * bat2 - batc
battery 3 * bat3 - batc
battery 4 * bat4 - batc
29. Does meter indicate battery string voltage of 49.5 V DC or higher?
If YES, then proceed to Step 30.
If NO, then continue with Step 29.
30. Visually inspect cable assembly between control & distribution panel and bat-
tery string. Replace cable assembly fuse and/or cable assembly until meter
indicates correct voltage.
31. Is this the last battery string to be installed?
If YES, then proceed to Step 31.
If NO, then repeat from Step 1 for next battery string.
32. Reconnect any battery strings disconnected for battery string voltage mea-
surement. Close and secure doors to battery compartment.
STOP. YOU HAVE COMPLETED THIS PROCEDURE.
POWER PLANT TEST POINTS
To measure * use test points
plant voltage * pv - pvr
plant current * pc - pcr
rectifier current:
rectifier 1 * rc1 - rr
rectifier 2 * rc2 - rr
rectifier 3 * rc3 - RR
Figure 4 – Control & Distribution Panel
PC
PV
RR
PVR
PCR
RC1
RC2
RC3
CB1
CB2
CB3
CB4
363-205-401
Issue 7, March 1997
normal
bat on
low volt
discharge
disconnect
Control & distribution
CB5
CB6
ed-83114-30

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SLC 5 Series and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents

Save PDF