5
(Optional) Install an Indoor Unit
This section applies to the scenario with three or four smart cooling products. The figures in
this document use the third cooling product as an example. If the fourth cooling product is
configured, refer to the installation method of the third cooling product. When the fourth
cooling product is installed, the layout of the control units are different. If there are only two
smart cooling products, skip this section.
Install the rPDU before installing the third and fourth smart cooling products.
5.1
Moving the Mounting Bar
1. (Optional) Remove the guide rails.
3. Remove an air baffle from the top of the front door of the cabinet shown in Figure (1),
rotate the air baffle by 180 degrees, and secure it to the top. Obtain the other four air baffles
from the fittings bag and secure them to the post on the front door.
2. Remove screws from the mounting bar.
7