FusionModule1000A20 Prefabricated All-in-One
Data Center
V200R003C10
Commissioning Guide
Issue
03
Date
2022-12-15
HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei FusionModule1000A20

  • Page 1 FusionModule1000A20 Prefabricated All-in-One Data Center V200R003C10 Commissioning Guide Issue Date 2022-12-15 HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei Digital Power Technologies Co., Ltd. and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 4 1 Safety Information. Issue 02 (2020-03-25) This issue is the second official release. ● Optimized section "Preparations and WebUI Login." Issue 01 (2019-07-15) This issue is the first official release. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 5: Table Of Contents

    7.1.1 Switching Between Two Power Supplies........................43 7.1.2 Commissioning the Logic Load Disconnection (Powering-Off) of the Power Supply System Under Normal Temperature...................................44 7.2 Cooling System Commissioning............................44 7.3 The Management System Commissioning........................45 Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 6 3. Setting the Transparent Transmission Function for the ECC800 Collector............92 9.3.3.3 Scenarios for Connecting the server........................94 9.3.3.3.1 Setting SMS.................................. 94 9.3.3.4 Scenarios for Connecting the LAN Switch......................96 Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 7 9.4.1 Commissioning Fire Extinguishing Devices (CE)....................107 9.4.1.1 Commissioning the Extinguishant Control Panel (CE)................... 107 9.4.1.2 Commissioning the Emergency Light (CE)......................108 9.4.2 Commissioning the ASD............................... 110 A Acronyms and Abbreviations................... 112 Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 8: Safety Information

    Equipment damage due to force majeure such as earthquakes, floods, volcanic eruptions, debris flows, lightning strikes, fires, wars, armed conflicts, typhoons, hurricanes, tornadoes, and extreme weather conditions ● Operation beyond the conditions specified in this document Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 9: Personal Safety

    D ANGER During operations, use dedicated insulated tools to prevent electric shocks or short circuits. The insulation and voltage resistance must comply with local laws, regulations, standards, and specifications. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 10 – Trained personnel: personnel who are trained in technology and safety, have required experience, are aware of possible hazards on themselves in Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 11: Electrical Safety

    WARNING For the equipment that needs to be grounded, install the ground cable first when installing the equipment and remove the ground cable last when removing the equipment. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 12 Installation personnel mark tightened bolts in blue. Quality inspection personnel confirm that the bolts are tightened and then mark them in red. (The marks should cross the edges of the bolts.) Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 13 If high touch current may occur on the equipment, ground the protective ground terminal on the equipment enclosure before connecting the power supply; otherwise, electric shock as a result of touch current may occur. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 14 (LSI) circuits. ● When touching the equipment and handling boards, modules with exposed circuit boards, or application-specific integrated circuits (ASICs), observe ESD Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 15: Environmental Requirements

    Do not place the equipment near heat sources or fire sources, such as smoke, candles, heaters, or other heating devices. Overheat may damage the equipment or cause a fire. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 16 Before opening doors during the installation, operation, and maintenance of the equipment, clean up any water, ice, snow, or other foreign objects on the top of the equipment to prevent foreign objects from falling into the equipment. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 17: Mechanical Safety

    Before installing equipment in a cabinet, ensure that the cabinet is securely fastened with a balanced center of gravity. Otherwise, tipping or falling cabinets may cause bodily injury and equipment damage. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 18 ● Move or lift the equipment by holding its handles or lower edges. Do not hold the handles of modules that are installed in the equipment. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 19 Set a restricted area and prominent signs for working at heights to warn away irrelevant personnel. ● Set guard rails and warning signs at the edges and openings of the area involving working at heights to prevent falls. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 20 If a single ladder is used, the recommended angle for the ladder against the floor is 75 degrees, as shown in the following figure. A square can be used to measure the angle. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 21 Do not drag steel ropes and hoisting tools or bump hoisted objects against hard objects during hoisting. ● Ensure that the angle between two hoisting ropes is no more than 90 degrees, as shown in the following figure. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 22: Equipment Safety

    Otherwise, the gas may leak and cause a fire. ● High-temperature pipes after welding must be promptly cooled. 1.5 Equipment Safety Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 23: Cooling System Safety

    Do not expose batteries at high temperatures or around heat sources, such as high-temperature sunlight, fire sources, transformers, and heaters. Battery overheating may cause leakage, smoke, flammable gas release, thermal runaway, fire, or explosion. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 24 Ensure that no liquid enters the equipment to prevent faults or short circuits. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 25 WARNING If the electrolyte leaks, absorb and neutralize the electrolyte immediately. Exercise caution when moving or handling a battery with electrolyte leakage, because the leaking electrolyte is hazardous. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 26 ● Batteries are damaged due to your or a third party's reasons, for example, relocating or reinstalling the batteries without complying with the Company's requirements. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 27 When installing batteries, do not place installation tools, metal parts, or sundries on the batteries. After the installation is complete, clean up the objects on the batteries and the surrounding area. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 28 Intake: Seek immediate medical attention. Special requirements for lead-acid batteries: NO TICE When the battery temperature exceeds 60°C, check whether the electrolyte leaks. If the electrolyte leaks, take proper measures promptly. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 29 If batteries are out of service life, contact a battery recycling company for disposal. ● Do not expose waste batteries to high temperatures or direct sunlight. ● Do not place waste batteries in environments with high humidity or corrosive substances. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 30: Precautions For Power-On Commissioning

    Operations marked as optional in chapters, sections, or procedures can be performed depending on the actual situation. ● Huawei assumes no liability for any loss caused by unauthorized changes to the initial configuration parameters. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 31: General Power-On Commissioning Process

    FusionModule1000A20 Prefabricated All-in-One Data Center Commissioning Guide 3 General power-on commissioning process General power-on commissioning process Figure 3-1 General power-on commissioning process Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 32: Preparations For Power-On Commissioning

    4 Preparations for Power-On Commissioning Preparations for Power-On Commissioning 4.1 Tool Preparations Table 4-1 Tools Tools Phillips screwdriver Flat-head screwdriver Utility knife Multimeter Electroprobe Network cable tester Cable tie Insulation tape Marker Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 33 Step ladder (2 m) ESD wrist strap Heat gun Point thermometer Adjustable wrench RJ45 crimping tool Wire stripper Flashlight Hand-held Heat shrink tubing Phase-sequence meter thermometer Clamp meter Insulation megohmmeter Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 34: Reference Document

    The ECC800/NetEco version depends on the version in use. Click on the ECC800/ NetEco WebUI to obtain the current version. 4.3 Commissioning Personnel Skill Requirements Below table describes the skill requirements for the FusionModule1000 commissioning personnel. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 35: Preparing For The Power Supply And Distribution System Power-On Commissioning

    Skill requirement: power distribution engineer NO TE For the diagrams and tables, see the initial configuration parameter manual for the solution in use. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 36: Preparing For The Cooling System Power-On Commissioning

    Step 3 Verify that the condensate drainpipe is not blocked. Step 4 Verify that there is no leakage point in the door, floor, or ceiling of the FusionModule1000. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 37: Preparing For The Management System Power-On Commissioning

    The passwords and parameters must be the same as those in the initial configuration parameter manual for the solution in use. ----End 4.7 Preparing for the Fire Extinguishing System Power- On Commissioning Prerequisites The FusionModule1000 has been installed. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 38: Optional) Auxiliary Heating For Extra Low Temperatures

    Smart cooling product: -30°C to +55°C NO TICE If the pre-fab. module interior temperature is beyond the normal operating range, condition the air to ensure that the temperature meets the operating requirements. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 39 NO TE When the auxiliary heater is heating the pre-fab. module, ensure that all pre-fab. module doors are closed to avoid heat loss and improve the temperature rising speed. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 40: Checking Before Power-On

    Document required: initial configuration parameter manual Skill requirement: power distribution engineer Checking Before Power-On Below table lists the items to be checked for the FusionModule1000 before power- Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 41 Power Measure the insulation of the There is no electricity cable power cables using an leakage in the power supply insulati insulation megohmmeter. and distribution system. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 42 Measure the frequency at the ● Frequency range for the ATS input end using a 50 Hz scenario: 49–51 multimeter. ● Frequency range for the 60 Hz scenario: 59–61 Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 43 Check the monitoring device ● Devices are installed ement nent installation and connection. securely as shown in the system installa monitoring device layout tion diagram. ● Cables are correctly connect connected. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 44 Check the lighting device ● Devices are installed in nent installation and connection. positions shown in the system installa lighting device layout tion diagram. ● Cables are correctly connect connected. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 45: Power-On Commissioning

    FusionModule1000 level by level. NO TE For equipment with dual power inputs, circuit breakers of both power inputs must be switched on. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 46: Normal Power-On Checking For Components

    ● ATS monitoring module has no alarms. ● Verify that the phase sequences of the two power inputs to the ATS are correct ● The AUTO LED indicator is on. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 47 Smart The PWR and RUN indicators are on. gateway The PWR, RUN, and ALM indicators are converter The PWR, RUN, and ALM indicators are sensor Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 48 Fire alarm The alarm indicator turns off. bell alarm indicator Extinguish on the ant abort extinguis button hant control Pressure panel switch Electrical actuator Horn strobe Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 49 Check Check Check Standard Item Item Warning sign (Optional) ASD power The ASD power indicator is on, and there power-on is no alarm in the management system. commissi oning Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 50: System Commissioning

    Step 6 Check whether the power supply to the downstream devices is normal. NO TE During the operation, if the power supply to the downstream devices is normal, the switchover between the two power supplies is successful. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 51: Commissioning The Logic Load Disconnection (Powering-Off) Of The Power Supply System Under Normal Temperature

    ----End 7.2 Cooling System Commissioning Before putting the FusionModule1000 into use, you must commission the cooling system to ensure normal cooling. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 52: The Management System Commissioning

    7.3.1 Preparing for Commissioning the Management System Tool Preparations Multimeter, network cable tester, and RJ45 crimping tool (Optional) Preparations for Modifying the Management System Initial Configurations Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 53: Commissioning The Management System

    Enter the initial user name and password on the ECC800 WebUI to log in to the ECC800 WebUI. Check the connections of all monitoring devices by referring to the monitoring device layout diagram. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 54: Fire Extinguishing System Commissioning (Ce)

    ● To avoid damage to the heat detector, keep a proper distance between the heating device and the heat detector during the commissioning. Preparations Tools: multimeter, smoke pistol, heating device, flat-head screwdriver, Phillips screwdriver, step ladder Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 55 Figure 7-1 Auto & Manual indicator position diagram Step 5 Check whether the extinguishant control panel displays any alarm. If an alarm is displayed, clear the alarm before performing follow-up operations. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 56 Step 7 Heat the heat detector using a heat gun until the heat detector indicator changes from blinking once every six seconds to steady on to trigger a heat detector FIRE RELAY alarm. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 57 Step 8 Check whether the electrical actuator has been activated. Step 9 Commission the pneumatic switch. Pull up the reset button on the pneumatic switch to short-circuit the cables within to simulate an extinguishant release. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 58 Wait for one minute and turn the Enable Control key rightward. After the LCD changes from EEE to Ad, press Reset on the extinguishant control panel to reset the extinguishant control panel. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 59 Figure 7-9 Loop 1 FAULT RELAY indicator on Hold the smoke detector, and rotate it clockwise to install it to the base. Step 11 Simulate a cable disconnection fault for the heat detector. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 60 Step 13 Flip the Enable Control key rightwards, reset the extinguishant control panel by pressing Reset on it, and then flip the Enable Control key leftwards to reset the key. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 61: Shutting Down And Powering Off

    During the power-off process, there is no fire or other exception, but the fire control panel displays a power failure alarm. Ignore the alarm. Step 4 Switch off the external input power circuit breaker of the FusionModule1000. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 62 FusionModule1000A20 Prefabricated All-in-One Data Center Commissioning Guide 8 Shutting Down and Powering Off NO TICE After power off, all circuit breakers should be in the OFF state. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 63: Commissioning Core Components

    ● The general PDF circuit breaker can be an ATS, MCCB, or MCB. (Optional) If an ATS is configured, go to Step (Optional) If an MCCB or MCB is configured, go to Step Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 64: Optional) Commissioning The Abb Ats

    CA UTION Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Switch on all SPD circuit breakers in the integrated UPS.
  • Page 65 Line 1-Switch I. Set the parameter based on site requirements. ● On the main menu screen, select device configuration and press . On the device configuration screen, you can set thresholds for parameters. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 66: Commissioning The Pd510 Electricity Meter

    Step 8 Set the ATS controller to auto mode. ----End 9.1.1.2 Commissioning the PD510 Electricity Meter Prerequisites You have powered on the power distribution equipment where the PD510 electricity meter is installed. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 67: Commissioning The Tp48400B

    CA UTION During the PD510 electricity meter power-on commissioning, you are not allowed to modify the initial configurations unless you are authorized by onsite Huawei engineers. Step 2 Set a protection password for the PD510 electricity meter. NO TE The Protection Password of the PD510 electricity meter can be set to a 4-digit integer ranging from 0000 to 9999.
  • Page 68 Step 6 Set parameters such as Battery connected, Rated capacity, BLVD Enable, Installation Time, and Volt. Detect Mode based on the actual configurations. NO TE Set the voltage test mode if the cable for monitoring single battery voltage is configured. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 69 Step 11 Observe the power system for 15 minutes. If no alarm is generated on the LCD during this period, the current and voltage for batteries and loads are normal. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 70: Commissioning The Tp48600B

    Step 2 Switch on the AC input circuit breaker and measure the output voltage on the AC input circuit breaker. The value should range from 85 V AC to 300 V AC. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 71 The batteries capaci capacit controlled by one y of circuit breaker or each fuse are called a battery battery string. string Other Install Current Parame ation time ters Time Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 72: Commissioning The Tp481200B

    DC power and supplies power to and backs up power for – 48 V communications equipment with a maximum output current of 1200 A. Preparations Tool: multimeter Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 73 Step 6 Set the number N of batteries connected, the rated capacity, and installation time based on site requirements. NO TE Set the voltage test mode if the cable for monitoring single battery voltage is configured. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 74 Other Installa Set this Parame tion parameter ters time to the current time. Step 7 Switch off the AC input circuit breaker. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 75: Commissioning The Cooling Devices

    The parameter can be modified only after you enter the correct password. Step 1 Turn on the general switch. Step 2 After the device is powered on, the screen is displayed after the system is initialized for 10s. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 76 On the Settings tab page, tap Set to set the ambient temperature and humidity. Figure 9-2 Temperature & humidity setting On the Settings tab page, tap Teamwork Settings to set teamwork parameters for multiple devices. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 77: Optional) Commissioning The Intelligent Heat Exchanger

    System Func > Diagnosis > SelfTest. NO TE For more details please see the documents delivered with the intelligent heat exchanger. Step 2 The smart cooling product operates properly after the self-test is successful. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 78: Commissioning Monitoring Components

    Step 1 Connect a network cable between the PC network port and the WAN1 port (protected by a security mechanism) on the ECC800-Pro. Table 9-6 Default IP addresses for the WAN and LAN ports on the ECC800-Pro Port Default IP Address WAN1 192.168.8.10 Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 79 Click the Advanced tab and select Use TLS1.1 and Use TLS1.2. (Optional) Click the Connections tab and select LAN settings. (Optional) On Proxy server, clear Use a proxy server for your LAN. Click OK. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 80 Choose Tools > Internet options > Security, choose Add the ECC800-Pro IP address to the list of trusted sites. Figure 9-5 Adding an address Enable file download and set the security level of the trusted site to low. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 81 WebUI login page. Figure 9-7 WebUI login page On the login page, enter the preset user name admin and preset password Changeme, set the language, and click Log In. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 82: Optional) Commissioning The Ibox And Ibat

    Current source 0–xxxA Hall The actual specifications of the Hall effect sensor prevail. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 83: Networking Iboxs And Ibats In Wireless Mode

    (iBattery 2.0) or short intervals (iBattery 3.0), and finally to blinking green at long intervals, the iBAT connects to the iBOX network. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 84: Optional) Neteco Management

    The subnet mask of all IP addresses is 255.255.255.0. Table 9-8 IP address list Item Preinstallation Setting Description Server IP 192.168.8.11 Used for logging in to the NetEco and address the PowerEcho. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 85: Obtaining The Neteco Software License

    Product Support > Network Energy > Data Center Facility > Fusion Modular Data Center > iManager NetEco 6000 at https:// support.huawei.com and apply for the license of the NetEco software by referring to the guide. 9.3.3.1.3 Powering On a Server This topic describes how to power on a server.
  • Page 86: Logging In To The Powerecho

    Step 1 In the browser address bar, enter https://192.168.8.11:32804, and then press Enter. NO TE 192.168.8.11 is the default IP address of the NetEco. Step 2 Enter the User Name, Password on the login page and click Log In. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 87: Installing The Ne Mediation

    ● After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 88: Neteco Menu Settings

    ● Make sure that the IP address of the NetEco server is not contained in the compatibility view website. Step 2 Enter the User Name, Password, and click Login. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 89: Loading A Neteco License

    Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 90 You can configure Management Info, Electricity Info, and Refrigeration Info for the equipment room management domain. Click on the toolbar. Repeat steps Step 2.1 Step 2.4 until the configuration is complete. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 91: Adding A Containerdc

    Step 4 Select ContainerDC from the Type drop-down list. Figure 9-9 Selecting the container Step 5 Select the ContainerDC to be added and drag the container icon to the Design area. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 92 ● In the Properties area, you can set properties, such as Text style, Font and Text background, for the text control. ● In the upper area of the current page, click Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 93 2. Add filter conditions, select multiple containers and click Delete. 3. In the displayed Confirm dialog box, click Yes. ● Delete one module. Select Modular and click Delete under Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 94 The batch deletion page is displayed. Figure 9-13 Deleting multiple modules in batches page Select multiples modules and click Delete. In the displayed Confirm dialog box, click OK. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 95: Process Of Adding A Device

    Click the device. The parameter setting area is displayed in the right pane. (5) Parameter Set device parameters in the parameter setting area. setting area (6) Save Click Save. The device is added. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 96: Scenarios For Connecting The Ecc800 Collector

    > WAN_1 Default 192.168.1.1 Set this parameter based on the gateway default gateway address assigned by the network administrator. Step 3 Set NetEco communications parameters on the ECC800 WebUI. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 97: Creating The Ecc800 Collector On The Neteco

    The IP address of the NetEco connected has been configured on the ECC800 WebUI. Procedure Step 1 Choose System > Configuration Management > Data Center Planning from the main menu. The Data Center Planning window is displayed. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 98 ● The modification of the device name on the ECC800 web client and the modification of the device name on the NetEco are synchronized with each other. Step 5 Click in the upper area of the page to save device information. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 99: Setting The Transparent Transmission Function For The Ecc800 Collector

    Enable Security Authentication is set to Enable by default. If so, an authentication password must be set. If Enable Security Authentication is set to Disable, there is no need to set an authentication password but this is risky. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 100 On the ECC800 WebUI, Enable Security Authentication is set to Disable. ● If Connection mode is set to Security protocol, enter the value of Confirm password that has been set on the ECC800 WebUI, and click Confirm. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 101: Scenarios For Connecting The Server

    ● Personal data such as phone numbers and Email addresses are anonymized in the NetEco GUI and encrypted in the NetEco during batch data transmission to ensure data security. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 102 Step 4 Click Apply to save the settings. NO TE ● Click Test to check the connection between the NetEco and the SMS modem. ● Click Reset to reset interworking parameters of the SMS modem. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 103: Scenarios For Connecting The Lan Switch

    Choose Local Configuration > Server configuration, and set the service IP address (VCN intranet IP address), NAT IP address (VCN external IP address), time zone and time according to the site requirements. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 104 ● The VCN automatically restarts after the IP address is modified. The restart takes about 5 minutes. After the restart, use the new IP address to access the VCN. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 105: Changing The Preset Password For The Vcn Servers

    Step 3 Enter Old Password, New Password, and Confirm Password and click Save. Figure 9-21 Changing a password 02 ----End ?.2. Setting Parameters on the VCN IVS Client Prerequisites The network communication between the VCN and the camera is normal. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 106 After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
  • Page 107 If you set the recording plan policy is to All, you do not need to set the recording plan time. Click Next to complete the recording plan setting. When is displayed in the status bar, the recording plan has been set successfully. Click Finish. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 108 Set other parameters based on the documentation delivered with the equipment or the documentation obtained by referring to the Preparing Documentation section, and click Finish. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 109: Configuring Camera Parameters On The Neteco

    Login User Indicates the user name Huawei123 for logging in to the IVS client. NOTE The Admin user cannot log in to the NetEco to connect to the VCN. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 110: Registering With The Ocx Plug-In

    Only after you register with the OCX plug-in, you can play videos recorded by the camera on the NetEco in real time. Procedure Step 1 Open Internet Explorer and choose Tools > Internet Options. Step 2 Click Security, as shown in Figure 9-24. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 111 Step 4 Enable ActiveX-related options for trusted sites. NO TE After ActiveX-related options are enabled, a message is displayed, indicating that the computer is prone to risks due to security settings. Ignore the message. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 112 Step 6 If the OCX plug-in needs to be registered on the client again, perform the following operations to uninstall the OCX plug-in and then re-install it: Close Internet Explorer. Find C disk directory folder exists eSDK_IVS folder, right-click to select Delete. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 113: Adding A Camera Using Automatic Discovery

    Step 2 In the left navigation tree, choose Discovery Camera. Step 3 On the Discovery camera page, add a camera by following the instructions provided in Figure 9-27. Figure 9-27 Adding a camera using automatic discovery Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 114: Commissioning Fire Extinguishing Devices

    Preparations Tools: none Documents: power supply and distribution system diagram, documents delivered with the extinguishant control panel, fire extinguishing system conceptual diagram (CE), fire extinguishing device layout diagram (CE) Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 115: Commissioning The Emergency Light (Ce)

    NO TE For the diagrams, see the initial configuration parameter manual for the solution in use. Procedure Step 1 Turn off the upstream switch of the emergency light power cable. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 116 The emergency light turns off, and the power indicator turns on. Step 6 Press the red button of the emergency light. The emergency light turns on. When you release the red button, the emergency light turns off. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 117: Commissioning The Asd

    Step 3 Release smoke in the protected area using the smoke pistol. Verify that the ASD alarm indicator lights up, and that an alarm is generated in the management system. Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 118 FusionModule1000A20 Prefabricated All-in-One Data Center Commissioning Guide 9 Commissioning Core Components NO TE After the operation is complete, press the reset button to reset the ASD. ----End Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 119: A Acronyms And Abbreviations

    A Acronyms and Abbreviations Acronyms and Abbreviations automatic transfer switch Conformite Europende power distribution cabinet power distribution unit rPDU rack power distribution unit uninterruptible power system video cloud node Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.
  • Page 120 FusionModule1000A20 Prefabricated All-in-One Data Center Commissioning Guide A Acronyms and Abbreviations very early smoke detection apparatus Issue 03 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd.