Checking For Correct Operation - Kodak X-Omat 270 RA Installation Instructions Manual

Hide thumbs Also See for X-Omat 270 RA:
Table of Contents

Advertisement

[1]
Remove the other external PANELS from the
PROCESSOR, and open the TOP COVER.
[2]
To allow correct operation of the LEVEL
SENSORS, add 500 mL (8 fl oz) of developer
to the DEVELOPER TANK and 500 mL
(8 fl oz) of fixer to the FIXER TANK.
[3]
Slowly, fill the DEVELOPER and FIXER
TANKS with water to the overflow limit.
If the RECIRCULATION PUMP does
not energize, check that the FIXER
and DEVELOPER TANKS are full. If
the TANKS are full and the
RECIRCULATION PUMP does not
energize, do the following:
a.
Connect the PORTABLE
COMPUTER using INTERFACE
CABLE TL-4391.
b.
Using the DIAGNOSTICS DISKETTE
699574, enter the ''Specific Mode'' to
manually operate the RECIRCULATION
PUMP.
c.
Energize the RECIRCULATION PUMP
for approximately 5 seconds to remove
air from the plumbing system.
d.
Return to normal operating mode.
[4]
Move the wall power switch to the ''ON''
position.
[5]
Move the CIRCUIT BREAKER CB1 on the
PROCESSOR to the ''|'' position.
[6]
When the electronics self-check is complete,
check that the WATER INPUT SOLENOID,
the DRYER BLOWER, and the DRYER
HEATER energize.
[7]
Check that water is draining smoothly.
[8]
With the PANELS removed, check the
complete plumbing system for leakage.
2B6843

Checking for Correct Operation

NOTE
CIRCUIT
BREAKER
CB1
H104_0389ACB
H104_0389AA
31

Advertisement

Table of Contents
loading

Table of Contents