1. Unscrew the cap of the seal wash reservoir.
2. Together with the cap, remove the seal wash line from the seal wash
reservoir.
3. Remove the peristaltic tubing from the seal wash pump. When the
tubing is removed, any liquid that may be present in the seal wash
line, flows off to waste.
To restart the device after a long-term shutdown, follow these steps:
1. Engage the peristaltic tubing in the seal wash pump.
2. Reconnect the seal wash line and the solvent lines to the
appropriate reservoirs.
3. Retighten the reservoir cap hand-tight. Verify that the retaining
guide remains in the hole in the reservoir cap. If it does not, press
the retaining guide into the hole to ensure that the tubing is kept in
place in the cap.
4. Turn on the device. Observe the following:
Situation
If the device remained in the system
stack and all system modules were
turned off.
If the device is restarted after transport.
5. Prepare and restart the other modules in the Vanquish system,
following the instructions in the Operating Manuals for the modules.
Pay special attention to the Preparing the Module for Operation
section.
6. Purge the pump and then have the pump deliver for a short time.
7. Before starting an analysis, let the device equilibrate and be sure
that it is ready for operation. See
(} page 95).
Action
Turn on the system with the system
power button on the system base.
Turn on the device with the main power
switch.
Preparing the Device for Operation
Pumps C, Pumps F ( VC-Pxx, VF-Pxx)
Operating Manual

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents