The Fundementals of Smoke Control

Testing the System

During the installation, you should perform operational tests that make
sure the components and subsystems of the smoke control system are
installed correctly. After the installation is done, you must perform
acceptance tests, to prove that the smoke control system is capable of
doing what it was designed to do. The testing procedures are covered in
a later chapter of this manual.
Bibliography
The National Fire Protection Association. NFPA 90A, Standard for the
Installation of Air Conditioning and Ventilating Systems. The National
Fire Protection Association.
The National Fire Protection Association. 1988. NFPA 92A,
Recommended Practices for Smoke Control Systems. The National Fire
Protection Association.
Underwriters Laboratories, Inc. UL 555S, Standard for Leakage Rated
Dampers for Use in Smoke Control Systems. Underwriters Laboratories,
Inc.
Underwriters Laboratories, Inc. UL 555, Fire Dampers. Underwriters
Laboratories, Inc.
Underwriters Laboratories, Inc. UL 864, Control Units for Fire-
Protective Signaling Systems. Underwriters Laboratories, Inc.
1-26
Infinity Smoke Control Guide
Technical Manuals Online! - http://www.tech-man.com

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Infinity and is the answer not in the manual?

Table of Contents

Save PDF