SECTION 8 - CONTROL COMPONENTS

Installation

1. Apply a light layer of thermo-conductive grease on
the new power module base plate.
3. Connect cables and connector back to the power
module as previously tagged.
NOTICE
DO NOT OVERTIGHTEN THE TERMINAL BOLTS, OR DAMAGE TO
THE UNIT COULD OCCUR.
4. After all connections to the power module are made
and verified, the battery can be reconnected.
8-14
Figure 8-23. Power Module Terminals
Figure 8-24. Cables on Power Module Post Terminal
– JLG Lift –
2. Install the power module with the AMP connector
upwards and secure to the chassis.
NOTE: Power module shown as installed on the
machine (AMP connector Upwards).
Tighten the power cables on controller posts with a
torque of 5.6 - 8.4 Nm (4.1 - 6.2 ft lb).
5. Install chassis rear shield and chassis covers.
6. Check software version (Refer to Section 9), if nec-
essary proceed with a software update.
7. Proceed with a system setup and calibration (Refer
to Section 9.3).