Specific Maintenance Work - DeDietrich C 340 Series Installation And User Manual

High-efficiency floor-standing gas boiler with diematic evolution scb-01, diematic evolution scb-10
Table of Contents

Advertisement

Fig.122
Connect the pressure gauge
10
5/6/7/8/9
2
2
3
Fig.123
Close the gas valve
Fig.124
Check the value
(+)
7
X mbar
11.4

Specific maintenance work

7762666 - v.02 - 29092020
2
3
2
AD-3001408-01
6
AD-3001409-01
AD-3001410-01
Perform the specific maintenance work if this proves to be necessary
following the standard inspection and maintenance work. To conduct the
specific maintenance work:
2. Open the screw in measuring point 2 of the gas control valve.
3. Connect a pressure gauge to measuring point 2 of the gas control
valve.
4. Switch on the boiler.
5. Set the boiler to low load.
6. Close the boiler gas valve very slowly until error code H.01.09
appears on the display.
7. Compare the measured value with the minimum value in the table.
Tab.127 Minimum gas pressure switch value
C 340
280
350
430
500
570
650
8. If the measured value is lower, set the gas pressure switch to the
correct value or replace it.
C 640
Minimum value
(mbar)
560
14
700
13
860
10
1000
10
1140
10
1300
10
C 340 / C 640
11 Maintenance
153

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents