Checking The Gas Leakage Monitoring (Vps) - DeDietrich C 340 Series Installation And User Manual

High-efficiency floor-standing gas boiler with diematic evolution scb-01, diematic evolution scb-10
Table of Contents

Advertisement

Fig.115
Negative (-) side of the air pressure
differential switch
12
(+)
14
X mbar
Fig.116
Preparing the gas circuit
4
3
P1
Fig.117
Connecting a hose
3
5
7
7762666 - v.02 - 29092020
10. Remove the syringe hose from the + side of the air pressure
11. Disconnect the silicon hose from the - side (P2) of the air pressure
12. Connect the - side of the air pressure differential switch the hose
13. Pull out the syringe very slowly until error code E.04.08 appears on
10
P
(-)
14. Check the pressure indicated by the pressure gauge at that point. This
2
11
P
(+)
1
13
AD-3001571-01
11.3.8
The VPS check consists of two actions: checking the VPS for leaks and
checking the switch value. Proceed as follows:
1. Switch off the boiler.
2. Close the boiler gas valve.
3. Remove the pressure from the gas pipe by unscrewing the screw in
2
4. As soon as the gas pipe is pressure-free, re-tighten the screw.
AD-3001572-01
5. Open the screw at measuring point 3 on the gas control valve.
6. Connect a hose to measuring point 3 of the gas valve.
5
2 P
3
6
AD-3001573-01
differential switch and reconnect the original hose.
differential switch.
coming from the T piece.
the display.
is the switch pressure.
A switch pressure between -5.5 and -6.5 mbar is good. A lower or
higher switch pressure indicates a problem with the air pressure
differential switch.

Checking the gas leakage monitoring (VPS)