Initial situation
4
Push the control gate to the left and hold it
(the interrogation lever locks in lower
position and the actuating opening for the
DISCONNECTING function opens).
802-9081.9 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • Revision 11
Bus sectionalizer panel with one three-position disconnector: Decoupling the
busbars
2
To decouple the busbars, open the circuit-
breaker.
5
Switch the three-position disconnector to
OPEN position (insert the operating lever
and turn 180° counter-clockwise).
3
Push the interrogation lever downwards
and hold it.
6
Remove the operating lever (the
interrogation lever and the control gate
return to their initial position).
Operation