Siemens NXPLUS C Installation And Operating Instructions Manual page 240

Medium-voltage switchgear, fixed-mounted circuit-breaker switchgear up to 24 kv, extendable, single busbar, metal-enclosed, gas-insulated
Table of Contents

Advertisement

Operation
1
Initial situation
4
Switch the three-position disconnector to
READY-TO-EARTH position (insert the
operating lever and turn 90° clockwise).
7
Push the locking device upwards.
240/293
Bus sectionalizer panel with one three-position disconnector: Earthing the right-
hand busbar
2
Push the interrogation lever downwards
and hold it.
5
Remove the operating lever (the
interrogation lever and the control gate
return to their initial position).
8
Fit a padlock.
Revision 11 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • 802-9081.9
3
Push the control gate to the right and hold it
(the interrogation lever locks in lower
position. The actuating opening for the
READY-TO-EARTH function opens).
6
To earth the busbar system, close the
circuit-breaker.

Advertisement

Table of Contents
loading

Table of Contents