Craning end panels
802-9081.9 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • Revision 11
For further information to usable lifting rods, see page 97, "Tools/auxiliary means".
Fig. 56:
Craning with lifting rods (diameter of lifting rods, 20 mm)
➭ Lower the transport unit onto roller pads, reinforced rollers or tubes (approx. 30 mm
diameter). Distribute the roller pads so as to support the transport unit at the outer edges
and at the joints between the panels.
➭ Lift one side, then the other side of the transport unit with roller crowbars and slowly lower
it on the mounting position. Apply the roller crowbars only at the corners of the transport
units.
In the end panels there are openings for inserting the crane rods in the side walls.
Fig. 57:
Openings for crane rods
➭ To insert the crane rods, undo the Torx bolts, push them upwards through the slot and
tighten them. The openings for the crane rods are released.
Fig. 58:
Releasing the openings for the crane rods
➭ Insert the crane rods into the openings.