Inspection; Machine Installation - Pro Mach Orion CTS Flex Stretchwrapper Manual

Stretch-wrapping equipment
Table of Contents

Advertisement

Machine Manual
CTS Flex Stretchwrapper
Introduction and Safety

Inspection

Note:

Machine Installation

Page 1-12
1. Remove all packing and supporting additions - these may include the blocks under the
carriage and the restraining bar over the table.
When removing the packing materials covering the machine, care
must be taken not to cut any of the electrical wires and/ or polyure-
thane covering on the film carriage rollers.
2. Perform a visual inspection of the electrical and mechanical parts for loosened joints
and / or broken connections. Any suspected shipping damage must be reported imme-
diately to the freight carrier. Any transport damage cannot be claimed to Orion Pack-
aging Inc.
Items that are vulnerable to damage and must be inspected are as follows:
Motors and transmissions
Junction boxes
Electrical conduits
Proximity and limit switches
Photocells
3. Check around the tower to ensure that there is no crippling of the movable parts i.e.
casters, center axle or drive assembly.
4. Verify the following:
Check wires and conduits for crushed sections or loose fittings.
Verify the film carriage to be sure that it is correctly aligned with the tower
Verify the tension on the lift belt.
Verify all the dials and knobs on the control panel for smooth action.
After the visual inspection has been completed, the electrical power and the com-
pressed air (Optional) shall be connected as specified on the diagrams supplied with
the machine.
An electrical diagram is provided with each machine in the envelope attached to the
panel box.
Make sure the machine is on a level surface.
Orion Packaging insist on a dedicated circuit be used for this wrapper. Extension cords
are not allowed and can void your warranty.
Orion
Revision 3.0
25 July 2016