Preparing The Cp System For Operation On The Field Bus; Operating Voltage; Saving The String Assignment - Festo CP-FB5-E Manual

Cp fieldbus node 5
Hide thumbs Also See for CP-FB5-E:
Table of Contents

Advertisement

2. Commissioning
2.1

Preparing the CP system for operation on the field bus

2.1.1 Operating voltage

2.1.2 Saving the string assignment

Festo P.BE-CP-FB5-E-EN en 0112a
Please note
S The CP field bus node must have a separate operating
voltage supply.
Please note
Before commissioning the CP system, you must first
prepare the CP system for commissioning (see manual
"CP system").
Before commissioning the CP system on the field bus, pro-
ceed as follows:
1. Connect the operating voltage of the node (see manual
"CP system").
2. Connect the CP modules.
3. Switch on the operating voltage.
4. Save the string assignment by pressing the SAVE key.
5. Switch off the operating voltage of the node.